How a Tree RemovalPermit Works
One trunk measurement decides your path
Follow a tree from the first measurement to the two-year check under Montclair's draft tree ordinance. Section numbers refer to the draft posted with the November 10, 2026 Council agenda, so you can check every step.
Start here
Measure the trunk
Measure the diameter 4½ feet above the ground, on the downhill side, and drop any fraction of an inch. Trees under 6 inches need no permit.
§324-2 "Diameter at Breast Height"6–23 in.
Average tree
or a conifer at least 20 ft tall
Apply
Application to the Township Arborist. $100 for up to two trees, $100 for each tree after that.
§324-5BDecision
Must be granted
within 20 days of a complete application. The Arborist checks the paperwork but cannot say no.
§324-5CReplace
| 6–12.99 in. | 1 tree or $450 |
| 13–23.99 in. | 2 trees or $900 |
Tier 1 preferred for the smaller size; at least one Tier 1 for 13 inches and up.
§324-6BWho sees it
The owner, the Township Arborist and the contractor.
24–35 in.
Significant tree
or a conifer at least 30 ft tall
Apply
The same application and $100 fee as an average tree.
§324-5BDecision
Must be granted
within 20 days of a complete application. The same review as an average tree.
§324-5CReplace
| 24–35 in. | 3 trees or $1,350 |
A "mix of Tier 1/2." No minimum number of Tier 1 trees is set for this size.
§324-6BWho sees it
The owner, the Township Arborist and the contractor.
Over 35 in.
Extraordinary tree
or a conifer at least 50 ft tall, or a State champion-size tree
Apply
$300 per tree. The application must address the 14 considerations in §324-5C, such as pruning, roots, drainage and heat.
§324-5BDecision
Can be denied
The Arborist writes a report and, within 20 days, grants, denies, grants in part or asks for changes. For construction, removal needs "clear and convincing evidence" certified by the Township Engineer.
§324-5C · §324-5H(1)Replace
| Over 35 in. | 4 trees or $1,800 |
At least two must be Tier 1 large-canopy trees.
§324-6BWho sees it
The owner, the Township Arborist and the contractor; the Township Engineer if building; the Zoning Board, then the courts, if appealed.
§324-11Also
Building on the lot
No construction permit until the tree permit is issued. No final certificate of occupancy until replacement trees are planted or paid for; a temporary one can be issued meanwhile. Trees cut in the two years before a development or construction application are reviewed as if still standing.
§324-5G · §324-5K · §324-5LAlso
Dead or hazard trees
A separate path at any size. A Licensed Tree Expert and/or ISA-certified arborist certifies the tree in writing, and it owes one replacement or $450. If the tree is an imminent threat, it can come down first and the paperwork can follow within 10 business days.
§324-2 · §324-5D · §324-5E · §324-6BAlso
Skipping the permit
Up to $2,000 per tree and up to 90 days of community service, each tree a separate violation, and every permit on the property voided. Contractors face suspension. A stop-work order can come from four Township officers.
§324-9 · §324-10Tier 1: a large canopy tree, at least 40 feet tall or 30 feet wide when grown. Tier 2: other approved species.
Invasive trees: trees on the Township's "prohibited" list need no permit and can be excused from replacement (§324-2, §324-7).
Based on the draft of Chapter 324 posted with the November 10, 2026 Council agenda. Sustainable Montclair · sustainablemontclair.org